Special Projects
Roosevelt City Nature Park
-
Strata Service Project group photo, October 2023
-
Asst. City Manager Ryan Clayburn explains the Strata Service Project tasks- October 2023
-
Strata Service Project participants
-
Healing Pond- No Fishing Notice
-
Freshly planted native Choke Cherry trees
-
Little Miss UBIC volunteers after helping to clear a trail
-
Paved parking lot in front of restroom
-
Paved path from UBMC to bridge
-
Amphitheatre with paved trail
-
Paved trail coming down from UBMC
-
Amphitheater
-
Arching trees over trail before paving
-
Nature Park Drawing
-
Areal view of fishing pond- August 2023
-
Fishing pond border- August 2023
-
Lodgepole fence made with reclaimed homestead fence posts
-
Crane placing Nature Park vault toilets - August 2023
-
Nature Park restrooms
-
Roosevelt City Nature Park Logo
-
Ariel view of the Roosevelt City Nature Park
-
Volunteers helping to cut the privative trail along the park's south ridge
-
Bridge With Grass
-
Golden Cottonwoods
-
Fishing pond
Nature Park Progress Footage
Roosevelt City Nature Park/ Cottonwood Creek Trail Project Details
Project Engineers: Sunrise Engineering
Project Cost for Phase I : Est. $1.2 Million
Budget: $1,979,000 Grant - $1,100,000 City
Funding: Utah Office of Outdoor Recreation, Utah's Watershed Restoration Initiative, Joint Highway Commission, Utah Department of Transportation, Tax Increment Funding, & Roosevelt City
Phase I
Nature Park 75% Complete
Cottonwood Creek Trail 10% Complete
Estimated Completion of Phase I: Spring 2024
Council Members Involved in Project:
Current Activity:
- Pond (DWR) Fish Pier
- Trail Seeding (DWR)
- Land Easements / R.O.W
- Fencing
- Trail Paving
- Pavilion
- Single Track Trail
Sports Complex Project Details
Project Engineers: Jones & DeMille Engineering
Project Cost: Est. $3.5 Million
Budget: $3,220,000 CIB Loan - $280,000 CIB Grant Anticipated Donations $100,000
Funding: Community Impact Board, Roosevelt City, & Community Partners
Phase I
15% Complete
Estimated Completion of Phase I: Spring 2024
Councilmembers Involved in Project:
Current Activity:
- Earthwork
- Water Lines
- Concrete Prep.
- Fencing
- Lighting
Shooting Complex Project Details
Project Engineers: Jones & DeMille Engineering
Project Cost: Est. $1.3 Million
Budget: $300,000 City – Anticipated Donations $170,000
Funding: WSFR & Roosevelt City
Phase I
10% Complete
Estimated Completion of Phase I: Spring 2024
Councilmembers Involved in Project:
Current Activity:
- Entrance Road
- 200 Yard Range
- Relocate Power Line
Shooting Benches
Teddy's Playground Project Details
Project Engineers:
Project Cost:
Budget:$25,000 - Arts, Parks, and Recreation Committee
Funding: Roosevelt City
Phase I
Council members Involved in Project:
Current Activity:
- Planning Front 9 of Disc Golf Course
- Staking Trail and Tee pads
- Parking Lot Construction
Teddy's Playground "Before"
Roosevelt City Innovation Hub
Innovation Hub Project Details
Project Engineers: CRS Engineers
Project Cost:
Budget: $229,000
Funding: RCIC Grant & Roosevelt City
Phase I
10% Complete
Estimated Completion of Phase I: Spring 2024
Councilmembers Involved in Project:
Current Activity:
- Design
- Bid Award